A timeline showing stages of construction in Medora

About The Project

Construction on the Medora Business Loop and City Section project began in fall 2024 and will continue through summer of 2026. The infrastructure enhancements will improve safety, traffic flow, and pedestrian access along Pacific Avenue (I-94 Business Loop) between exits 24 and 27. The work is vital as Medora prepares for the Theodore Roosevelt Presidential Library opening and the additional traffic it will bring to the city.

The NDDOT has worked closely with city officials, local business owners, and the public to develop a traffic solution that benefits the entire community.

Key features of the project include:  

  • Roundabout installation to improve traffic flow at Pacific Avenue and Chateau Road.
  • Bridge widening to expand the Little Missouri River bridge including a left-turn lane and a shared-use path.
  • Roadway upgrades, including fresh pavement along Pacific Avenue from I-94 Exits 24 to 27, decorative lighting and landscaped medians in select areas.
  • Pedestrian accessibility and ADA enhancements, including new crosswalks and upgraded pedestrian ramps.
  • Chateau Road reconstruction, including a shared-use path, new signage, a center turn lane and other roadway upgrades.

Project Updates

Construction Progress

  • Pacific Ave: Curb, gutter, shared-use path, and paving complete.
  • City section: Drainage, ADA sidewalks/curbs, and medians complete.
  • Roundabout: Construction complete.
  • Little Missouri River Bridge: Expansion nearly finished; final work wraps spring 2026.
  • Chateau Road: About 85% of concrete paving complete. Temporary asphalt in place where concrete paving will be laid next year. Sidewalk, landscaping, and remaining paving resume in 2026.

Traffic Impacts

  • Pacific Ave/Chateau Road roundabout is fully operational. Traffic will continue to be routed along the north side of the bridge, with taper in the median barriers allowing a safe transition between the bridge and roundabout.
  • Roadway is fully open to traffic with no flagging operations. Shared-use path will not fully accessible through winter months.

Project Goals

  • Estimated Project Cost:
    $28.4 Million
  • Estimated Completion:
    Spring/Summer 2026

Areas/Traffic Impacted

Pacific Avenue I-94 Business Loop Chateau Road

Frequently Asked Questions

A “Welcome to Medora” sign will be installed as part of the project. The design and aesthetics were developed in consultation with members of the city council.

The temporary roadway will remain in place until portions of the Little Missouri bridge are widened, and the roundabout is complete, which is expected by late summer or early fall. Lanes will stay 11 feet wide.

Crews will update pavement markings at the Chateau Road intersection and coordinate with the Billings County Sheriff’s Department for safe traffic control during the Medora Musical season. NDDOT will coordinate logistics with the contractor for the annual All Horse Flag Parade. Pile driving is expected to be completed by summer, minimizing construction noise.

Project Location

Contacts

Heather Brew
Transportation Construction Administrator, NDDOT
hbrew@nd.gov
Alternative Contact
Mike Njos
Project Engineer, Civil Science
mnjos@civilscience.com