GRAND FORKS, N.D. — Concrete pavement repair work continues at Interstate 29 interchanges between Exit 145 and Exit 138 in Grand Forks. Traffic at multiple interchanges will remain reduced to a single lane through November.
Crews are grinding the pavement to improve ride quality and are placing temporary pavement markings. Message boards will be posted to guide motorists through the work zones. Traffic control will remain in place until this phase of work is complete.
The project was originally scheduled to finish this fall, but additional concrete pavement and bridge repairs extended the timeline. Completing those repairs now will extend the life of the interchanges and reduce future lane closures. Crews will return in spring 2027 to finish permanent pavement markings and seeding.
The North Dakota Department of Transportation reminds drivers to slow down, stay alert and be prepared for changing traffic patterns in work zones.
Up-to-date road conditions and construction information can be found by calling 511 or visiting the ND Roads map at travel.dot.nd.gov.