Bid Opening Date - November 20, 2026 9:30 AM CT

Submitted Questions for Job 23896 - SS-6-032(075)231

Just want to confirm that double cells will not be allowed. Only Single Cells, correct? for all 4 sites?

DOT Response

For all sites on this project, only single cell boxes will be allowed.

Submitted: 10/30/2026 10:30:24 AM

Answered: 10/30/2026 10:53:05 AM

Bid item 78, 30" approach pipe. Bid sheet has 430' but the allowable list and plan pages add up to 332'. What is the correct total needed?

DOT Response

Bid Item 714-4113, Pipe Conduit 30 IN - Approach will be updated in the Estimate of Quantities on the Addendum. Correct total is 332 LF. 

Submitted: 10/28/2026 3:16:16 PM

Answered: 10/29/2026 8:27:21 AM

What style of flap gate is required for bid item 80? Waterman F10 or a standard steel flap gate for CSP.

DOT Response

Either are allowable. 

Submitted: 10/28/2026 12:56:31 PM

Answered: 10/28/2026 1:31:33 PM