Regarding note 704-P04, does this mean things like topsoil stripping, pipe extensions, class 5 placement, etc. can't happen on opposite sides of the road at the same time or is the intent just to prevent drop offs on the both sides at the same time?
DOT Response
The roadway lanes are only 13' wide. if traffic is shifted to 11' lanes, that gives the contractor room on one side to coulter cut and widen the roadway and do pipe extensions. They can shift traffic to close the other shoulder down to do the widening and pipe extensions on the other side. This will only work where we have the 3" overlay and Widening typical section. The subcuts and curve corrections will be full reconstruct and will have to utilize single lane traffic as described in the work zone traffic control plans.
Submitted: 10/8/2026 3:02:39 PM
Answered: 10/9/2026 8:10:30 AM