Submitted Questions for Job 24770 - NH-3-002(181)278

In regards to the milling and paving operations of the multi-lanes, would it be acceptable to pave a single lane more than one day's run in advance of the adjacent lane in order to eliminate putting live traffic on the milled surface? This is referencing Std Specs. Sec. 430.04H.1. Par. 7.

DOT Response

This would be acceptable as the project is less than 6 miles. 

Submitted: 4/3/2026 1:47:26 PM

Answered: 4/6/2026 11:44:15 AM

Per Plan Note 411-P01, Is it the intent that the excess milled material stockpiled at the NDDOT DL Yard be processed through a separate operation, i.e. crushing, to meet the maximum particle size of 1.5"?

DOT Response

The intent of the note was for the DOT to receive a usable product free of chunks larger than 1.5". It is up to the contractor to come up with an operation that achieves that specification. 

Submitted: 4/3/2026 1:41:11 PM

Answered: 4/6/2026 10:18:16 AM