Bid Opening Date - February 27, 2026 9:30 AM CT

Submitted Questions for Job 24102 - NH-4-083(157)181

SP 244(25) provides Existing IRI Data in Appendix A for the Northbound Lanes, yet the project is being done on the Southbound Lanes. Can we get the Existing IRI Data for the Southbound Lanes?

DOT Response

Response Pending.

Submitted: 2/6/2026 7:32:00 AM

Answered: