Is the earthwork summary table on sheet 1 of section 11 correct? It seems that some material is being double paid under common excavation - waste and common excavation - type A.
For example, right of CL for NHU-5-094(160)903, it shows that there is 29,201 CY of common excavation - type A but only 8,449 CY of embankment and 20,752 CY of waste. Shouldn't this be a total of 29,201 CY of excavation with 8,449 CY of Type A and 20,752 CY of common excavation waste?
DOT Response
The Common Excavation – Type A quantities on Section 11 Sheet 1 are incorrect. An addendum will be issued for the correction.
Submitted: 2/5/2026 10:13:56 AM
Answered: 2/10/2026 4:33:00 PM