Bid Opening Date - November 14, 2025 9:30 AM CT

Submitted Questions for Job 24672 - SC-3026(055)

Shoulder Preparation plan note refers to prepping the area where the mountable curb and gutter goes; 1,120 LF The bid quantity for shoulder preparation is 1.88 miles. Is this correct ? If so, what does shoulder preparation entail outside of where the curb and gutter goes ?

DOT Response

The requirements for shoulder preparation are outlined in Section 230 of the Standard Specifications, and the plan note addresses additional requirements specific to this project. The total bid quantity of 1.88 miles is correct and represents the full length of shoulder preparation along the project.

Submitted: 11/12/2025 3:04:50 PM

Answered: 11/12/2025 4:03:32 PM