Submitted Questions for Job 23645 - HEU-1-981(134)

In Section 110 Sheet 2, the Mast Arm Street Name signs are "to be furnished and installed by others" but the flat sheet quantities are in the Flat Sheet bid item. Please verify if these will be "furnished and installed by others", or if they need to be quoted for install under the bid item for flat sheet. If they are to be bid as install, please provide the sign specs and dimensions.

DOT Response

Mast arm street name signs (19th Street x2 and Century Ave x2) are to be furnished and installed by the City as noted on the plan sheet 110-2. The Flat Sheet quantity on sheet 110-1 does not include the square footage for these signs nor does the quantity on sheet 8-1.

Submitted: 11/7/2025 10:01:40 AM

Answered: 11/10/2025 9:59:28 AM

Can you clarify the median tie bar (into curb) requirements: if they are needed or if there is supposed to be expansion only adjacent to the curb & gutter? There is no detail, and the typical sections are inconsistent with what is required. Two proposed typicals have tie bar on one side of the median only, one typical has no tie bar in it and one has tie bar on both sides. According to detail drawing D-750-2, the concrete median does not have tie bar tying into curb and gutter, only expansion joint.

DOT Response

The typical sections are not inconsistent with what is required, we will require what is shown. The City prefers to have additional ties in certain situations and the typical sections show this. The tie bars are desired by the City (for settlement reasons) and therefore needed only in situations where new median concrete will be next to existing curb that does not have a ledge. Standard detail D-750-2 shows only expansion adjacent to the curb but this shows new curb that has the ledge. The two typical sections you mention with ties on one side only is because one side will have new curb and gutter with a ledge, therefore no ties needed, and the other side will be new median concrete next to existing curb and gutter without a ledge, therefore ties needed. The typical section with no ties shown is because both sides will have new curb and gutter with a ledge. Expansion will still be needed as shown in the standard detail, for both scenarios.

Submitted: 11/6/2025 9:35:22 AM

Answered: 11/6/2025 12:41:01 PM

There are 1728 Tons of Aggregate Base Class 5. How does the excavation get paid for? We didn't see a bid item for that.

Answered with Addendum.

Submitted: 10/29/2025 7:59:27 AM