Bid Opening Date - November 14, 2025 9:30 AM CT

Submitted Questions for Job 23575 - SS-1-031(022)000

760-P01 - RUMBLE STRIPS: Cut the shoulder, centerline, and intersection rumble strips a minimum of 14 days after completion of the Seal Coat. With the 14-day wait period on the RUMBLE STRIPS, would the requirement be to FOG SEAL the road after the CHIP SEAL and prior to the RUMBLE STRIPS, and then come back and FOG SEAL the RUMBLE STRIPS after they are cut in? Or can the contractor wait to FOG SEAL until after the RUMBLE STRIPS are cut in?

DOT Response

The fog seal that is placed on the chip seal can be completed after the rumble strips are cut in. 

Submitted: 11/10/2025 11:29:46 AM

Answered: 11/12/2025 9:09:54 AM