Our review of the contract documents shows a requirement for a “Contractor’s Laboratory” per Section 706 of the NDDOT Specifications. As noted in Section 706, this laboratory is intended for the Quality Control (QC) testing required under Section 430, “Hot Mix Asphalt.”
After reviewing the plans and bid items for this project, we do not see any work that includes hot mix asphalt placement. Since there are no Section 430 QC tasks required, we would like clarification on whether the Contractor’s Laboratory provision is still applicable to this project.
DOT Response
Response Pending.
Submitted: 9/27/2025 8:15:40 AM