HIGHWAY: 294
PROJECT_DESC: FGO-12TH AVE N BNSF RAILROAD BRIDGE
COMMENTS: Speed limit on structure 25 MPH. Two way traffic on structure. One lane each direction.
WIDTH_RESTRICTION: 11
HIGHWAY: 94
PROJECT_DESC: SE CASS DIKE INSTALLATION
COMMENTS: No lane closures set up and speed limits are normal. Work done being done behind the barriers
HIGHWAY: 94
PROJECT_DESC: W FGO 9TH ST/I-94 SEPAR (SURCHARGE)
COMMENTS: Barriers and attuneation devices are present. Speed limits normal.
HIGHWAY: 81
PROJECT_DESC: FARGO-52ND AVE S (I-29 TO UNIV DR)
COMMENTS: Jersey Barriers have been installed on both shoulders thru a 300 ft construction zone on 52nd Ave S, from 31st St to 25th St. The maximum lane width is 11ft. 52nd Ave is closed from 25th Street to University Dr. The traffic on 52nd Ave is detoured around on 25th St to 58th Ave to University Dr.
WIDTH_RESTRICTION: 11
HEIGHT_RESTRICTION: 11
HIGHWAY: 29
PROJECT_DESC: I-29 AT 52ND AVE S.-RAMP & STRUCTURE
COMMENTS: I29 & 52 A Interchg; I29 SB single lane closure, 12' width, 3'shldr lt, 2' shldr rt, 16.2' height restr., exit traffic SB at 52 A use temp. loop RP 60.359. NB I29 single lane closure with 14' width plus 4' shldr rt, 16' height. NB I29 wide loads use ramp detour (overhd. 52 A.) RP 60.441
WIDTH_RESTRICTION: 12
HEIGHT_RESTRICTION: 16
HIGHWAY: 29
PROJECT_DESC: I-29 & 52ND AVE S NW & NE FRONT ROAD
COMMENTS: 31st str. S.& 38th str. S. have been closed for reconstruction, north & south bound traffic will have to seek alternate routes.